Cumulative across projects delivered to date. Irrigation schemes range from half an acre to a thousand acres, greenhouses from a sixty square metre tunnel to twenty hectares of multi-span, and solar installations from 100 W to 5 kW, with larger arrays delivered as design and site supervision. Topographic surveys and farm layouts have been completed at sites in Nyeri, Embu, Thika, Nakuru and Laikipia, and water master plans prepared for estates up to 1,000 hectares.
Surveys
GNSS survey with RTK
Points recorded with a GNSS rover against a base station established on site, giving centimetre positions on UTM projection so that levels, boundaries and set-out all sit on one referenced framework.
Surveys
Topographic survey drawing
Survey reduced to a drawing at half metre contour intervals on UTM projection and Arc 1960 datum, with every beacon scheduled by northing, easting and elevation, referenced to the stated survey control.
Surveys
Stream gauging and yield measurement
Flow measured in the channel with a current meter on a wading rod, velocity taken across the section and paired with the wetted area, so that the abstraction a scheme is designed around is a figure that was measured rather than estimated.
Surveys
Ground control and set-out
Base station set over a control point and the position held for the survey, then the same framework used to set out structures on the ground so that what is built matches what was drawn.
Surveys
Aerial survey, commissioned and controlled
Where a site is too large or too broken to walk, the flight is commissioned from a specialist operator while Criserve sets the brief, establishes and checks the ground control, and reduces the returned model to the drawings and volumes the design is built on.
Irrigation
Open field drip irrigation
Dripline run along ploughed rows across the block, with line spacing, emitter rate and zone size set from the crop, the soil and the flow available, so that pressure holds to the last emitter in every zone.
Irrigation
Sprinkler irrigation
Pop-up sprinklers set into planted beds on a spacing that gives head to head coverage at the working pressure, with the arc adjusted at each head so water reaches the planting and not the paving.
Irrigation
HDPE pipeline jointing
Mainlines jointed by electrofusion under a controlled welding cycle recorded by the machine, with preparation, alignment and joint records appropriate to the pressure pipe specification.
Boreholes
Borehole drilling supervision
Drilling supervised against the hydrogeological siting report, with strata logged as the hole advanced and casing and screen set to the water strikes actually encountered rather than to a standard depth.
Boreholes
Test pumping and equipping
Step and constant rate test pumping with drawdown and recovery measured to establish the yield the source will actually sustain, then equipping with the pump, rising main, control gear and headworks sized on that tested figure.
Boreholes
Borehole logging and water strike verification
Instrument and cable reel set over the casing to log the completed hole, confirming depth, casing and screen position and the water strikes against the driller record before the pump is selected.
Water conveyance
Sedimentation tanks in series
Tanks set in series down the fall of the ground, each sized on a retention time long enough for the silt load to drop out, to reduce the sediment load before storage. Downstream irrigation filtration is selected for the water quality and emitter specification.
Water conveyance
Aeration cascade and weirs
Level weirs between chambers, set so that flow spreads across the full crest and falls in a sheet, aerating the water as it passes and distributing it evenly into the chamber below rather than scouring one corner.
Water conveyance
Intake and screening
Bar screen at the inlet chamber sized on the flow and on the debris the source actually carries, set at a spacing that holds back trash without blinding, and reachable for raking without entering the channel.
Water conveyance
Settling basins and storage
Basins built in parallel so that one can be taken out for desilting while the others carry the scheme, with the outlet drawn off below the surface and above the silt bed to protect the quality delivered downstream.
Water features
Hotel porte cochère cascade
An architectural water feature at the hotel porte cochère, with cascading water integrated into the arrival frontage and illuminated steps.
Water features
LED lit frothy nozzle water fountains
An architectural water feature with frothy nozzle fountains and integrated LED lighting, creating illuminated aerated water jets within a landscaped setting.
Greenhouses
Multi-span greenhouse block
A production block of multi-span houses set out in bays across the site, with the runs oriented to the prevailing wind, drainage taken between the blocks, and each bay valved so that crops at different stages irrigate on separate schedules.
Greenhouses
Tunnel structure
Hoop frame with purlins tying the arches, cover tensioned to shed rain without ponding, insect netting to the side walls for ventilation, and a masonry edge holding the cover down and keeping surface water out of the bed.
Civil works
Drainage channel and cutoff
A cutoff channel excavated to a designed section and gradient to intercept surface flow before it reaches the cropped ground, carrying it away at a velocity that moves the water without scouring the invert.
Civil works
Earthworks and compaction
Fill placed and compacted in layers by vibrating roller to the design section, with each layer checked before the next is placed so that the finished formation carries load without settling unevenly.
Waste management
Treatment chambers
Reinforced concrete chambers with baffle walls cast to divide the tank into settlement and digestion compartments, so solids are retained and only clarified liquid passes to the next stage.
Waste management
Cover slab and access
Cast cover slab with sealed access openings over each compartment and an inspection cover at the outlet, set flush with the finished ground so the tank can be desludged and rodded without breaking anything open.
Renewable energy
Ground mounted solar array
Array sized against the daily pumping schedule and the abstraction the source can sustain, on galvanised ground frames set at the tilt and row spacing that avoid self shading through the year.
Renewable energy
Inverter and controls
Inverter, protection gear and controls wired into a weatherproof enclosure, with the switching arranged so the pump can run from solar, generator or grid without reconfiguring the installation.
Renewable energy
Solar drying tunnel
A drying tunnel with tiered mesh beds and a gravel floor, ventilated to carry moisture out of the structure and sized so that coffee, grain or herbs dry evenly without direct sun on the product.
Renewable energy
Biogas digester
A bag digester in service and holding gas, bedded in a trench cut to the design profile with feed and outlet set to the working levels, the offtake run to the point of use and the digestate returned to the land.